PRINCE2 Foundation Sample Exam Questions

Should you be interested in attending a PRINCE2 training course and completing the PRINCE2 Foundation certification exam, here are some example questions to test your knowledge on.

    1. Which role is responsible for providing the user’s quality expectations?
      1. Executive
      2. Senior User
      3. Project Manager
      4. Senior Supplier
    2. Which of the following is not included in the Quality Register?
      1. Quality criteria
      2. Quality check method
      3. Quality responsibilities
      4. Planned quality check date

    3. Which process is triggered by a request to authorize a stage?
      1. Starting up a Project
      2. Directing a Project
      3. Managing a Stage Boundary
      4. Managing Product Delivery

    4. Which is a purpose of the Risk Register?
      1. To define the procedures for risk management
      2. To define the scales to be used for assessing a risk
      3. To act as a repository for all risks
      4. To document the risk budget

    5. Which describes a change budget?
      1. Funds set aside to accommodate estimate shortfalls
      2. Money to fund responses to known risks
      3. Funds that can be used for expanding the project scope
      4. Is a budget used for the development of products

    6. Which of the following is not part of the Benefits Management Approach?
      1. Scope of benefits to be reviewed
      2. Risks to each benefit
      3. How benefits are to be reviewed
      4. Who will review the benefits

    7. Which of the following is the PRINCE2 definition for a project?
      1. A series of activities to deliver an output
      2. A structure established for the management and control of a temporary and unique initiative
      3. A temporary organization created for the purpose of delivering one or more business products
      4. A series of routine activities required for day to day control

    8. Which of the following roles can the Project Manager also perform?
      1. Project Assurance and Team Manager
      2. Team Manager and Project Support
      3. Team Manager and Senior Supplier
      4. Project Executive and Senior User

    9. What is an objective of Starting up a Project process?
      1. To ensure the work required for initiation is planned
      2. To establish a management and control structure for the delivery of the project’s products
      3. To ensure the project is fully justified before work can commence on the specialist products
      4. To assess achievement of objectives

    10. To whom should the Team Manager report an exception situation?
      1. Project Board
      2. Project Manager
      3. Project Assurance
      4. Corporate management

    11. To whom should the Project Manager report an exception situation?
      1. Project Executive
      2. Team Manager
      3. Project Assurance
      4. Corporate management

    12. Which process is triggered by ‘work package authorized’?
      1. Starting up a Project
      2. Directing a Project
      3. Managing a Stage Boundary
      4. Managing Product Delivery
    13. Which role should not perform the role of Project Assurance?
      1. Executive
      2. Senior User
      3. Senior Supplier
      4. Project Manager
    14. Which is an objective of Initiating a Project?
      1. To determine how the quality required will be achieved
      2. To identify the pre-requisites for project initiation
      3. To plan project closure
      4. To enable the project management team to focus on product delivery
    15. Which is an objective of Starting up a Project?
      1. To determine how the quality required will be achieved
      2. Individuals appointed to carry out work in the initiation stage
      3. To plan project closure
      4. To enable the project management team to focus on product delivery
    16. Which is an objective of Controlling a Stage?
      1. To determine how the quality required will be achieved
      2. To identify the pre-requisites for project initiation
      3. To plan project closure
      4. To enable the project management team to focus on product delivery
    17. Which is an objective of Directing a Project?
      1. To determine how the quality required will be achieved
      2. To identify the pre-requisites for project initiation
      3. Ensure the project remains viable
      4. To enable the project management team to focus on product delivery
    18. Which of the following is not an element of the PRINCE2 model?
      1. Processes
      2. People
      3. Specialist techniques
      4. Practices
    19. Which is not one of the seven aspects of performance?
      1. Time
      2. Benefits
      3. Specialist techniques
      4. Sustainability
    20. Which is the purpose of the PRINCE2 Plans practice?
      1. To control unacceptable deviations
      2. Identify, assess and control uncertainty
      3. Facilitate communications and control
      4. To define a means in which user’s quality expectations can be met
    21. Which is the purpose of the PRINCE2 Risk practice?
      1. To control unacceptable deviations
      2. Identify, assess and control uncertainty
      3. Facilitate communications and control
      4. To define a means in which user’s quality expectations can be met
    22. Which is the purpose of the PRINCE2 Progress practice?
      1. To control unacceptable deviations
      2. Identify, assess and control uncertainty
      3. Facilitate communications and control
      4. To define a means in which user’s quality expectations can be met
    23. Which is the purpose of the PRINCE2 Quality practice?
      1. To control unacceptable deviations
      2. Identify, assess and control uncertainty
      3. Facilitate communications and control
      4. To define a means in which user’s quality expectations can be met
    24. Which is the purpose of the PRINCE2 Issue practice?
      1. To ensure changes to the project are controlled
      2. To define a structure of accountability
      3. To support a decision on a project’s ongoing viability
      4. To define a means in which user’s quality expectations can be met
    25. Which is the purpose of the PRINCE2 Business case practice?
      1. To ensure changes to the project are controlled
      2. To define a structure of accountability
      3. To support a decision on a project’s ongoing viability
      4. To define a means in which user’s quality expectations can be met

    The above questions are copyright of prince2training.com.au and should not be copied without the written permission of prince2training.com.au.

    Visit here for sample PRINCE2 Practitioner Exam Questions

Contact Us

Contact Us Form

This field is hidden when viewing the form